Story = what happened. Business Masterclass = how I would solve it.
Decision note 04 of 04 · Make the call
What should leadership approve today, and how do we stay in control after approval?
Approach
I state the recommendation first, back it with the numbers, and attach a gated roadmap: money follows evidence, every risk has a trigger and an owner, and the decisions needed today are explicit.
The decision
Approve S2 for ₹21.1 Cr, released in three gated tranches, starting with ₹9.9 Cr now.
Stage 04 of 04 · about 6 minutes · Excel build optional
LearnThe idea
State the recommendation first, then attach a gated plan in which money follows evidence.
SeeOn the case data
The recommendation matrix, the gated roadmap, risk triggers with owners, and the nine-slide storyline.
DoYour turn
Rebuild each exhibit from the raw data in Excel, then make one call yourself.
DecideWhat leadership does
Recommendation: approve S2 Moderate, ₹3.6 Cr EBITDA against −₹30.9 Cr if nothing changes, for ₹21.1 Cr of investment released in gated tranches.
Exhibit 4.1
Building the recommendation
Which option should management approve, and on what evidence?
Decision dimension
S1 Conservative
S2 Moderate
S3 Aggressive
S4 No change
Business impact: EBITDA (₹ Cr)
−10.9
3.6
−15.5
−30.9
Financial return: ROI
3.6x
1.6x
0.6x
—
Investment (₹ Cr)
5.6
21.1
27.1
11.5
Cash: net cash flow (₹ Cr)
−14.5
−17.3
−49.3
−46.9
Execution risk (5 = safest) · bandwidth
4.5 · Low
3.5 · Medium
1.5 · Very high
1.5 · High
Time to impact: payback (months)
3.3
7.3
21.1
—
Sustainability: exit run-rate uplift (₹ Cr a year)
25.8
47.7
26.0
—
Decision score
4.00
4.54
2.10
1.19
Source: Quick_Commerce_Case.xlsx · 2 Analysis, sections 6c, 6e and 6f
SeeWhat it shows
S2 Moderate is the only option with positive EBITDA and the highest exit run-rate uplift (₹47.7 Cr a year). S1 is safer but leaves value unclaimed; S3 adds risk and burns cash; S4 lets losses compound.
DecideSo what for management
Recommendation: approve S2 Moderate, ₹3.6 Cr EBITDA against −₹30.9 Cr if nothing changes, for ₹21.1 Cr of investment released in gated tranches.
DoHow it’s built in Excel
Data
Option outcomes (sheet 2 §6e-6g); decision score.
Approach
Compare all four options across business impact, return, investment, cash, risk, time to impact and sustainability; select the option that wins on balance and state why each alternative loses.
Month 9 · Re-weightMove money to levers that deliver; stop the rest
Month 12 · CloseRealised vs plan; choose the next 12-month option
Source: Quick_Commerce_Case.xlsx · 2 Analysis, sections 7a and 7b
SeeWhat it shows
Money follows evidence: ₹9.9 Cr now, the rest only when discount, contribution per order, store losses and EBITDA hit their gates. Thresholds tighten gradually, so the plan is demanding but not front-loaded.
DecideSo what for management
Each gate has an owner and a consequence: pass and release, miss and re-plan. Write that into the approval.
DoHow it’s built in Excel
Data
Gate KPIs and funding tranches (sheet 2 §7a-7b); owners (§7c).
Approach
Set Month-12 targets from the S2 plan; derive Month-3, 6 and 9 gate thresholds from the share of improvement due; tie each tranche to a gate.